Performed a comprehensive audit of existing water, wastewate...read more »r, and storm water SCADA systems, which consisted of proprietary hardware and software developed by HSQ Technologies. SCADA was comprised of a 20 year-old central computing infrastructure and remote devices at over 200 sites. The Audit defined present and future SCADA requirements, and evaluated and decided how to best meet those requirements. ArcSine's Audit developed a roadmap which clearly defined the sequence, timing, costs, staffing and other aspects of the SCADA migration. ArcSine's work products were suitable for planning, budgeting, and usable by technical and managerial personnel. « read less
Electrical engineering support for decommissioning the Humbo...read more »ldt Bay Nuclear Power Plant. Support included electrical design and supporting calculations for phased decommissioning of various elements of the Humboldt Bay Power Plant. « read less
Novato Sanitary District - RWF Expansion Job 1617.00
ArcSine designed electrical and control system improvements ...read more »for improvements to the Novato Sanitary District's in-service Recycled Water Facility (RWF) to increase the Plant's capacity from 0.85 MGD to 2.55 MGD. « read less
ArcSine Engineering provided both engineering services durin...read more »g construction and complete PLC and SCADA programming for a major upgrade to increase the capacity of the Novato Sanitary District's primary Recycled Water Facility, located in Novato, California. « read less
ArcSine provided electrical and control system engineering s...read more »upport for water system improvements for the City of Tulelake, California. Improvements included a complete rehabilitation of the Well No. 1 site, the addition of a standby generator at Booster Pump Station No. 1, including an Automatic Transfer Switch (ATS), the addition of a standby generator and ATS at Well No. 3, the addition of an ATS at Lift Station No. 2, and consolidation of the power distribution system at the corporation yard (BPS, Well No. 1, and Lift Station No. 1). « read less
DSRSD - Field Operations Facility-Electrical Improvements SDC/Construction Mgmt Job 1622.01
ArcSine provided engineering services during construction an...read more »d construction management for construction of electrical improvements to the Dublin San Ramon Services District's (DSRSD) operations Facility (FOF) in Pleasanton, CA. The project replaced the existing 1000-Amp service entrance, installed an 80kW emergency standby generator, including an automatic transfer switch (ATS), installed a 30kVA uninterruptable power supply (UPS) to provided redundant power to DSRSD's critical Supervisory and Data Acquisition (SCADA) system, installed a programmable logic controller (PLC) panel which interfaced with the District's 186Hz microwave backbone telemetry system and 4.9 GHz remote site radios, and a building-wide ArcFlash study. « read less
NASA-Ames Research Center is currently undergoing a NASA Con...read more »struction of Facilities (CofF) projects to replace the air-to-tube heat exchanger used to cool the heated gases that exhaust from the Aerodynamic Heating Facility (AHF) Arc Jet. ArcSine work included design, furnishing and installing, and testing electrical and controls integration aspects of the work. « read less
Dublin San Ramon Services District - Lift Station LS1 Radio Path Study Job 1650.00
ArcSine performed field radio testing using a 4.9 Coltz ...read more »;Subscriber module and access point, to verify a suitable radio path to integrate a remote lift station site into the District's SCADA system. The field testing identified the location (site) on the District's 186GHz microwave backbone ring best suited to receive the lift station telemetry. ArcSine's deliverables consisted of a report which include radio test data. « read less
Las Gallinas Valley Sanitation District Secondary Improvements Support - SDB/SDC Job 1663.03
Provided design review support and value engineering on beha...read more »lf of the District and performed coordination with Contractor during construction for electrical and control systems. « read less
Bella Vista Water District - Telemetry Replacement Job 1702.00
Downloaded new GE MDS Orbit radio software onto District-sup...read more »plied laptop and trained BVWD staff on programming the new radios. Assisted Bella Vista Water District (BVWD) in configuring all the radios at the BVWD Water Treatment Facility. Helped BVWD develop a strategy to complete installation and testing of radios. Developed basic test procedures and set up troubleshooting scenarios. « read less
Northern California & Oregon Engineering Company serving Redding, the Bay Area, and the surrounding Northern California area, as well as Medford, Rogue Valley, Willamette Valley, Southern Oregon, Central Oregon, Nevada, Washington, Idaho, Utah, and Arizona.