7 X 10 Wind Tunnel Drive Job 0474.00
Furnished, installed, and programmed a PLC system which cont...read more »rolled the air system valving and temperature control of the wind tunnel. « read less
Designed, furnished, and installed a SCADA system covering a...read more » 12-site municipal water system. Designed, programmed, and provided startup assistance for pumping station PLCs. « read less
Designed electric power distribution and street lighting for...read more » a 3,500-acre project. This project included lighting of residential, commercial, and industrial streets throughout the unincorporated area north of Medford, Oregon, identified as White City. The work also included the development of detailed lighting standards, now published and in use by Jackson County for all Developer projects in White City. ArcSine designed lighting within several White City subdivisions. « read less
Delta Diablo Sanitation District Electrical/I&C Improvements Job 0642.00
Designed electrical, instrumentation and controls, and SC...read more »ADA for treatment plant expansion to provide cooling water to 880-MW power generation plant. Feeds were designed for flexibility and included the following: 480-volt commercial power source, 480-volt source from power plant 21-kV source from power plant, with unit substation at cooling water facility « read less
Designed a 4-MVA transmission class substation with a downst...read more »ream overhead 12kV distribution circuit. Also included site power, lighting, and monitoring and controls. « read less
Developed three upgrade options and ultimate design of the c...read more »hosen options for the Gibraltar Pump Station. Also conducted field investigation and coordination with the electric utility for shutdowns to determine actual capacity of the existing switchgear and utility feeder bussing. Design work required to provide for future additions. « read less
Iron Mountain Mine - SCADA Telemetry Upgrade Job 0777.00
ArcSine Engineering was contracted to update and replace the...read more » existing SCADA software and PLCs for the wastewater treatment plant. This plant is part of the Environmental Protection Agency’s Superfund site’s effluent contamination mitigation process. The goal of this project was to reduce the risk of potential discharge of highly contaminated heavy metal leachate into the upper Sacramento River. The site’s SCADA system monitors and controls all aspects of the leachate treatment process, including regulating the release of treated water into the river. « read less
Northern California & Oregon Engineering Company serving Redding, the Bay Area, and the surrounding Northern California area, as well as Medford, Rogue Valley, Willamette Valley, Southern Oregon, Central Oregon, Nevada, Washington, Idaho, Utah, and Arizona.